A new infrastructure project, set to transport large amounts of electricity from Sudbury to Barrie, is moving forward.
Hydro One has started the process to build a new transmission line that will run from the Hanmer Transformer Station (TS) in Sudbury to the Essa TS near Barrie.
The following is a conversation with Hydro One’s Vice-President of Strategic Projects and Partnerships, Sonny Karunakaran. The North Star asked about the communities the proposed line would pass through, key project details, and other related issues.
Q: What is the project about?
“This specific project is a 500-kilovolt, single-circuit transmission line that comes from the Hanmer Transformer Station (TS) in Sudbury to the Essa TS near Barrie.
Once built, the line would ensure the north-south transmission capacity that’s presently in place gets expanded and strengthened to unlock future generation opportunities.
Ontario is growing, and so is the need for electricity right across this province, especially in Northern Ontario. That region is expected to grow rapidly over the next 25 years, as investments in new homes and businesses are being made. Infrastructure like this will support the North now and into the future.”
Q: What is the line going to look like?
“We are in the early stages of the project, and we are looking for feedback from stakeholders, business councils, local communities and members of the public to help inform the way we’re gonna develop the project.
We use that information to help shape how we’re actually going to wrap the project, (define) the type of structure we’re using and how we’re going to develop our construction methods and techniques. If people have any feedback they want to share with us, they can email Community.Relations@HydroOne.com.”
Q: What communities would the line pass through?
“We know the two end locations of the line (Barrie and Sudbury), but we still have to define the study corridor to make a determination on what the potential routes are and then evaluate them.
We would first get in touch with members of the public near the end locations, then develop a website to share what we heard and identify some of these study corridors … We then use that feedback to whittle down to various route options.
If you were to look at a map and see what the options are around those corridors (to connect the stations in Sudbury and Barrie) … there’s a high likelihood for the line to traverse the Parry Sound-Muskoka area.”
Q: Are there any other new lines like the one proposed?
“There are 15 other transmission line projects in the province. Some of them are like the Sudbury-Barrie line that are just commencing, others are in the middle stage of the process, others are under construction, and we already have one energized and finished.”
Q: When can people expect to see the project finished?
“This project is expected to be energized and in service by the end of 2032 … if we need to have the line in service by 2032, we would need to start construction at the beginning of 2029. That gives us roughly three years to do the outreach with members of the public, perform infield studies, environmental and archeological assessments, and then get the approvals form the Ontario Energy Board and regulators.”
For more information, visit the Hydro One website.