Hydro One Transmission Line Project: Round 2 Open Houses Announced

The proposed 300-kilometre high-voltage transmission line from Sudbury to Barrie is moving forward quickly, and Hydro One has announced its Round 2 Community Consultations for this summer, introducing narrowed-down “Focused Study Areas.” This round of meetings centers on new geographic maps that dictate the specific bands where the transmission line will actually be built. Because the existing infrastructure cannot safely support the weight or electrical clearance of these new 500-kV lines, Hydro One must build entirely new, larger steel structures and widen the existing right-of-way corridor.

For property owners, the lines drawn on these maps this summer will directly determine where massive new towers are placed, which shorelines will face extensive clear-cutting and visual disruption, and where heightened erosion risks could threaten sensitive ecosystems.

Attend a Summer In-Person Community Open House

Hydro One is hosting eight local, in-person drop-in sessions and two virtual webinars over the summer. If you want to view the localized parcel maps, speak face-to-face with project planners, or voice concerns over tower placement or environmental footprints, look for a meeting near your community:

Unable to attend an in person session? You can join a virtual community open house on Monday July 27, 2026 from 6 to 7 p.m. or Monday August 10, 2026 from 6 – 7 p.m. Details for the in-person sessions and registration details for both virtual sessions can be found on the project webpage here.

Project Timeline: What Comes Next?

With the province fast-tracking this infrastructure, Hydro One has outlined the following timeline for the project:

  • Round 2: Focused Study Areas – Summer 2026 (Current)
    • Hydro One is hosting summer meetings to share narrower geographic study corridors based on the data and feedback collected this spring
  • Round 3: Route Alternatives Announced – Late 2026
    • Hydro One will announce specific route options, triggering a third round of public open houses and comment windows
  • Preferred Route Chosen & Environmental Assessment (2027)
    • The final preferred corridor route will be officially selected, and the formal Class Environmental Assessment (EA) process will begin
  • Construction Begins (2029)
  • Line Officially in-service (2032)

GBA supports the long-term goal of strengthening the provincial electrical grid to support economic growth, but we strongly advocate for responsible development. As this fast-tracked initiative moves forward into its next phase, we will continue to attend upcoming open houses and provide targeted comments—advocating for robust environmental mitigation strategies are locked in to protect ecosystem health and water quality across our affected communities along the route.

Read more about the project here.